Tight Timelines for Dove Holes Investment Project

Tight Timelines for Dove Holes Investment Project

May 19, 2022
Over the Easter Bank Holiday weekend the team at Dove Holes quarry undertook a massive investment project to replace the 26 tonne rotor using 500 tonne crane.

Over the Easter Bank Holiday weekend the team at Dove Holes quarry undertook a massive investment project to replace the 26 tonne rotor using 500 tonne crane.

The overall investment cost £500,000 and was completed to very tight timeline, in just six days!  The job has only been done twice in the last 25 years.

A massive thanks to everyone involved, from employees and contractors working over the Easter Bank Holiday, those in Planning and those controlling the various teams and aspects of the job.  A fantastic team effort and fantastic achievement.