Impeccable Planning Pays Off
December 02, 2021
Last week, the North West Readymix Team supported their customer, Ward and Burke Ltd at Project Protis, a development of a new energy to waste plant.
For this job CEMEX was part of a three-way split of a 1,950m3 pour, working with two other suppliers. Six concrete pumps were set up at 5.00am, which then started pumping at 5.30am. The technicalities of this job meant that strong coordination was vital, with the delivery taking over four weeks to plan.
Danny Roberts commented: “The success of this job was down to a great effort by our operations at Ellesmere Port and Widnes plants, along with our Shipping Team at Preston Brook, overseen by our Technical Team on site. This was a very challenging day for all but was safely executed, thanks to the fantastic commitment and coordination by the CEMEX team.”